Latest Updates
Roadworks on Farrant Road commencing 7th April- Remedial works and resurfacing
Remedial works will be carried out along Farrant from 7th April for a duration of 8 weeks. During this period, there will be ‘road narrowing’ traffic control to provide a safe working environment for our operatives.
Once the remedial works are completed, final surfacing will be carried out. This will be completed in phases, with traffic diversions implemented to enter and exit Boyton Place via the road north of the site, as illustrated below.
We will endeavour to minimise the inconvenience and disruption that may occur.


Updated Images and Video
Please see below for a selection of images around the scheme, along with a video.













Phase | Status |
1 | Complete and occupied |
2a | Complete and occupied |
2b | Complete and occupied |
3a and the Local Centre | Awaiting decision notice Commencement date TBC |
3b | Construction underway |
4a, 4b and 5b | Application submitted |
5a and 5c | Planning permission granted and awaiting commencement |
6 | 80% constructed and occupations underway |
Phase | Status |
LEAP and Open Space between Phases 1 and 2 | Complete and in use |
NEAP and MUGA East of Phase 3b | Equipment to be installed in Spring 2025 Landscaping to be carried out in Autumn 2025 (To be delivered approximately 2 years ahead of schedule) |
LEAP and Gym Trail West of Phase 6 | Equipment to be installed in Spring 2025 Landscaping to be carried out in Autumn 2025 |